Whittington Hospital – Mental Health Transition Area

Whittington Hospital – Mental Health Transition Area

Summary of Project:

New mental health waiting rooms were needed for Whittington Hospital within the level 2 A&E mental health transition area. The project required several electrical services to be installed, with special attention being given to the colour change lighting as it was needed to aid the mood of patients using the waiting rooms.

A few of the electrical systems that were required included the modification to the lighting installation (including new anti-ligature luminaires and RGB colour change control), relocation of existing data cables (and addition of new where it was required), and the modification to the existing small power, fire alarm, nurse call, access control, and panic alarm systems. The installation of a new CCTV system was also required.

 

 

Site Addresses:  The Whittington Hospital, Magdala Avenue, London, N19 5NF

Programme:  6 Weeks

Client:  The Whittington Health NHS Trust

Principal Contractor:  Cuffe Plc

Consultant: Stuart McCurry & Partners

Architect: Ansell & Bailey Architects

Project Value: £55,000